When to use it
Prices look different but scope or term is unclear.
Normalize scope, price, capability, risk, service, implementation, and contract terms before a polished proposal or low headline fee decides the outcome.
A monthly fee can conceal a different service frequency, a start-up charge or excluded work. Use this calculator to compare two or three proposals over the same number of whole years. Enter USD amounts from written proposals, including known exclusions needed to deliver your common scope.
All amounts are in USD. Monthly fees increase once per year at the entered rate. Annual extras stay fixed; start-up costs apply once. Enter 0 only for a confirmed zero cost. An unknown exclusion means the proposal is incomplete, even when the arithmetic is available. Your entries stay in this browser tab and are not submitted to TrustPoint.
| Proposal | Base fees | Start-up + extras | Total | Evidence status |
|---|
This calculation compares entered costs. It does not select a vendor, verify insurance or licensing, assess service quality, predict inflation, or establish an approved budget. Resolve missing scope and cost evidence before relying on a comparison.
Hypothetical example, not actual vendor quotations: A quotes $2,000 per month, $1,000 start-up, $3,000 required annual extras and a 3% annual increase on the base fee. B quotes $2,200 per month, $0 start-up, $500 annual extras and no increase. Assume both cover the same service and all required costs are confirmed.
A’s base fees are $24,000 in year 1, $24,720 in year 2 and $25,461.60 in year 3. With $1,000 start-up and $9,000 extras, its total is $84,181.60. B’s base fees total $79,200; adding $1,500 extras gives $80,700. B costs $3,481.60 less over this period despite its higher monthly fee. If A’s extras were omitted, the comparison would reverse incorrectly.
For N years, the total is: one-time start-up + N × annual extras + the sum of 12 × monthly base fee × (1 + increase / 100)y, for y = 0 through N − 1. The increase affects the base fee from year 2. Calculations retain precision until displaying each result to two decimal places; displayed components may differ from their total by one cent.
Include taxes and pass-through charges in the relevant input if they apply to your common scope. This model excludes partial years, discounts, financing, mid-year increases, variable usage and changes to service volume. It calculates nominal cash cost, without a present-value adjustment. A percentage cap is an input limit, not a forecast. If the contract uses a different pricing rule, use its actual year-by-year schedule instead.
Preserve the scope revision and clarification log with the calculation. Use the criteria below to document non-price evidence, and the scope-writing guide to resolve mismatched service definitions.
A fair comparison begins with one scope, one instruction set, one clarification process, and one deadline. Each bidder should identify assumptions, exclusions, staffing, service evidence, options, price adjustments, and transition needs in the same structure.
The score supports judgment; it does not replace it. Leadership should document the strongest evidence, material gaps, residual risks, conflicts, reference findings, negotiation conditions, and reasons for the final decision.
Select only criteria relevant to the procurement. Define weights before proposals are opened and require evaluators to support material scores with proposal references or verified findings.
59 criteria shown
| Category and criterion | Evidence to request | Normalization question | Warning sign |
|---|---|---|---|
| Scope · HighRequirement coverage | Line-by-line response to the controlled scope | Are all bidders pricing the same required outcome? | Proposal silently omits difficult tasks |
| Scope · HighAssumptions and exclusions | Consolidated assumptions and exclusions schedule | Which condition would change price timing or responsibility? | Key exclusions appear only in fine print |
| Scope · HighService frequency | Task frequency and seasonal calendar | Does the frequency match property demand and standards? | Proposal uses phrases such as as needed without limits |
| Scope · HighDeliverable evidence | Sample reports logs photographs and closeout records | What record proves each material task was completed? | Completion relies on verbal assurance |
| Scope · MediumInterfaces with others | Responsibility matrix for management staff and other vendors | Where could a handoff leave work unowned? | Shared responsibilities are not assigned |
| Commercial · HighBase fee | Complete base pricing by period and unit | What exactly is included in the comparable base amount? | Low headline price excludes routine work |
| Commercial · MediumOptional services | Unit-rate or fixed-price optional schedule | Which likely activities create extra charges? | Common services have no stated rate |
| Commercial · MediumPass-through charges | Administrative surcharge delivery and material rules | Are markups and reimbursables handled consistently? | Undefined fees can be added later |
| Commercial · HighPrice adjustment | Renewal escalation index and notice terms | How could price change during the proposed term? | Increase language is discretionary |
| Commercial · MediumPayment terms | Invoice timing milestone and dispute terms | Does payment follow verified service or accepted milestone? | Large advance payment lacks protection |
| Capability · HighComparable experience | References for similar asset type scale and complexity | Has the proposed team delivered this exact scope? | Examples are unrelated to the property |
| Capability · HighNamed team | Names roles resumes licenses and allocation | Are the people presented the people assigned? | Key personnel are unconfirmed |
| Capability · HighWorkload capacity | Current commitments staffing ratio and mobilization plan | Can the team meet response and scheduled work together? | Capacity is asserted without numbers |
| Capability · HighSubcontractor control | Subcontractor list qualification and oversight process | Which obligations are delegated and how are they verified? | Material work may be assigned after award without review |
| Capability · HighQuality control | Inspection audit defect and corrective-action method | Who independently verifies quality? | The same person performs and accepts the work |
| Risk · HighInsurance evidence | Certificates endorsements limits and renewal process | Does evidence satisfy the contract and property requirements? | Coverage is promised but not documented |
| Risk · HighSafety program | Safety manual training incident and site-plan samples | How will property-specific hazards be controlled? | Generic policy does not address site work |
| Risk · HighLicensing and permits | Applicable licenses registrations and permit responsibility | Who verifies current authority before work starts? | Responsibility is shifted back to the client |
| Risk · MediumBusiness continuity | Backup staffing supply and disruption plan | What happens if the assigned crew or supplier is unavailable? | One individual or supplier is a single point of failure |
| Risk · MediumClaims and disputes | Claims history disclosure and escalation process | How are service disputes documented and resolved? | Material history is incomplete or evasive |
| Service · HighResponse standards | Acknowledgment attendance resolution and escalation targets | Which clock starts for each priority? | Only vague responsiveness is promised |
| Service · HighEmergency coverage | On-call roster escalation and mobilization protocol | Who responds when the primary contact fails? | Coverage depends on informal availability |
| Service · MediumCommunication method | Sample service report issue log and meeting cadence | How will open issues remain visible? | Updates arrive only after complaints |
| Service · MediumResident interaction | Conduct accessibility privacy and complaint protocols | What behavior and information rules apply on site? | No property-facing service standard exists |
| Service · HighPerformance measures | Proposed KPI definitions sources and thresholds | Can each measure be verified from source records? | Measures reward activity rather than outcomes |
| Implementation · HighMobilization plan | 30 60 and 90 day implementation plan | What must be complete before the start date? | Mobilization begins after service commencement |
| Implementation · MediumData and access needs | System access credential key and record checklist | What access is necessary and how will it be controlled? | Shared credentials are expected |
| Implementation · HighInventory and baseline | Initial condition inventory and exception method | How will pre-existing conditions be separated from new performance? | No agreed starting baseline is planned |
| Implementation · MediumTraining and orientation | Site orientation and role-specific training plan | What must personnel demonstrate before unsupervised work? | Training is limited to a brief tour |
| Implementation · HighTransition support | Incoming outgoing and client responsibility map | Who owns each handoff record and date? | Transition relies on the incumbent's goodwill |
| Contract · HighTerm and renewal | Proposed term notice and renewal language | Do all bidders use the same comparison period? | Automatic renewal hides inside notice language |
| Contract · HighTermination rights | Termination cause convenience cure and assistance terms | Can the property exit safely if performance fails? | Exit requires long notice or undefined fees |
| Contract · HighChange control | Written scope price and schedule change process | Who can direct and approve changed work? | Field requests can become unpriced extras |
| Contract · HighIndemnity and liability | Proposed allocation and limitations for professional review | Does risk allocation match control of the work? | Liability is broadly shifted away from the vendor |
| Contract · MediumRecords and audit | Record retention access and invoice support terms | Can the client verify billed and completed work? | Supporting records are proprietary or unavailable |
| Contract · HighCloseout requirements | Warranties manuals releases permits training and final records | What must be complete before final acceptance? | Final payment is disconnected from closeout |
| Selection · HighConflict disclosure | Ownership referral and relationship disclosure | Could any relationship influence the recommendation? | Potential relationship is not documented |
| Selection · HighReference validation | Comparable client contacts and permission | Which claim should references confirm? | References are pre-scripted or unreachable |
| Selection · MediumInterview consistency | Standard scenarios and scoring instructions | Did every bidder receive the same questions and time? | Interviews are informal and incomparable |
| Selection · HighTotal evaluated cost | Normalized multi-year cost with likely options | What is the probable cost for the same service outcome? | Selection compares only base fees |
| Selection · HighValue and residual risk | Decision brief covering strengths gaps mitigations and tradeoffs | What risk remains with the property under each choice? | Highest score is treated as an automatic decision |
| Selection · HighClarification control | Written question answer and addendum register | Did every material clarification reach all bidders? | Private verbal commitments alter one proposal |
| Selection · HighApproval record | Scoring conflict checks recommendation and authority record | Can an independent reader reconstruct the decision? | Award basis is missing from the minutes |
| Scope · HighSite condition acknowledgement | Dated walkthrough notes and disclosed constraints | Did each bidder price the same observed conditions? | One bidder assumes access or condition that others exclude |
| Scope · HighAcceptance criteria | Sample inspection and sign-off method | How will the client know a deliverable meets the agreed standard? | Proposal names tasks but no acceptance test |
| Scope · MediumSeasonal demand planning | Seasonal work calendar and capacity assumptions | Can staffing meet peak property demand? | Peak periods are priced as unforeseen extras |
| Scope · HighAsset list alignment | Asset register mapped to proposed service | Which equipment or areas are outside the quoted scope? | Critical assets are absent from the proposal |
| Commercial · HighEmergency callout rate | Rate card minimum charge and after-hours terms | What will a realistic emergency call cost? | Emergency prices are left for later agreement |
| Commercial · MediumCredits and missed service | Credit formula and service failure terms | How is undelivered work reflected in the bill? | Full payment is due despite missed scheduled service |
| Commercial · MediumTax and permit allocation | Schedule of included taxes and permit costs | Which public fees or taxes are included? | Proposal shifts material fees to the owner |
| Capability · HighSupervisor availability | Named supervisor workload and escalation coverage | Who can resolve a site problem when the assigned team cannot? | Supervisor is shared without realistic availability |
| Capability · MediumTraining evidence | Training matrix for named roles | Can the team perform the required work safely and consistently? | Qualifications are asserted without records |
| Risk · HighSubcontractor insurance | Subcontractor roster and coverage evidence | Do lower-tier parties meet the same relevant requirements? | Prime vendor cannot identify its subcontractors |
| Risk · HighIncident notification | Proposed notification timeline and report sample | How quickly will the property learn of an incident? | Notification duty is vague or delayed |
| Service · MediumException reporting | Sample monthly exception report | Will unresolved issues remain visible until closed? | Reports list activity but omit open failures |
| Service · MediumAccessible resident contact | Channel and response plan for affected residents | Can users receive timely understandable updates? | Only one unsuitable channel is offered |
| Implementation · HighFirst-month verification | Thirty-day checkpoints and acceptance measures | How will early delivery problems be found and corrected? | Mobilization ends without a verification stage |
| Contract · HighNotice delivery method | Exact notice clause and address controls | Can the client exercise rights before a deadline? | Notice procedure depends on an outdated contact |
| Selection · HighPredefined weighting | Approved criteria and weights before bids arrive | Were priorities set before reviewing prices and names? | Weights change after preferred bidder emerges |
A calculated total is only as reliable as the scope, quantities, assumptions, and risk allocation behind it. Show uncertainty instead of presenting a false point estimate.
Define what each score means, require a short evidence note, and reconcile large evaluator differences before totals are used. Keep mandatory failures and material risks visible outside the weighted score.
Before award, convert commitments into the final contract, implementation plan, service levels, reporting requirements, named-team provisions, insurance requirements, change control, remedies, records access, and closeout obligations.
Issue one controlled scope, document assumptions and clarifications, normalize price and service units, verify capability and risk evidence, score with disclosed criteria, identify residual risk, check comparable references, and preserve the decision record.
Price is one decision factor. Compare the cost of the same scope and service outcome, including likely options, exclusions, staffing, transition, risk allocation, quality controls, evidence, and contract terms.
Use the same scenario-based questions, time, participants, and scoring definitions. Ask the proposed delivery team to explain how it will handle property-specific conditions, then verify material claims in writing.
No. Qualified legal, insurance, engineering, safety, licensing, tax, accounting, and other professionals should review the matters within their disciplines.
A fictional proposal has a lower recurring price but excludes work included in a competing offer. The comparison cannot be completed until scope and additional costs are understood.
Original fictional example · no completed client assignment or property inspection is represented.
| Record to obtain | Review question or calculation |
|---|---|
| Common scope and quantities | Compare the same duration and delivery basis |
| Written exclusions | Keep unknown extras marked incomplete |
| Confirmed one-time and recurring costs | Separate arithmetic cost from a selection recommendation |
Useful working output: A normalized comparison with unresolved scope differences visible.
Open each challenge to test the reasoning against a different finding.
Check: Request a written price for the omitted visit and confirm frequency, mobilization and disposal costs using the same service period for both proposals.
Decision effect: Compare the clarified full scope. Keep an unresolved price visible as unknown rather than treating the omitted visit as free.
Check: Check named staffing, mobilization dates, relevant references and replacement arrangements against the property schedule.
Decision effect: Treat service readiness as a separate selection condition; the lowest total cost does not resolve a delivery gap.
Adapt the record request to authorized access, governing documents and the actual property. The example does not verify any unknown input or replace a professional conclusion.
Proposal Scoring: Mandatory Gates and Weight Sensitivity · More vendors and management selection examples
Prices look different but scope or term is unclear.
Do not rank monthly fees before normalizing the service basis.
Reconcile total-term fees, required extras, exclusions and unresolved pricing assumptions for each proposal.
Original proposed coordination checks · adapt to authorized access, the actual obligation and the appropriate professional review. These are not findings about your property.
Follow the related handoff workflow · Read the review definitions
If one bid includes disposal and access equipment and another excludes them, compare an adjusted common-scope cost before scoring price. Mark missing prices as unresolved rather than assuming zero.
Require evidence for staffing, credentials, insurance, service coverage, subcontracting, and implementation. Separate disqualifying requirements from scored preferences.
Keep clarifications, the evaluated revision, scoring rationale, and conditions for award. Check that the executed agreement preserves the scope and service levels used in the comparison.
Find checklists and data definitions · Explore vendors and management selection
Bring each proposal to the same service period, quantities and completion standard.
Scroll horizontally to read all columns.
| Criterion | What to check | Practical implication |
|---|---|---|
| Whole cost | Include mobilisation, recurring charges, exclusions, maintenance and expected replacement. | The lowest initial bid may omit work necessary to deliver the intended outcome. |
| Sensitivity | Recalculate after changing the assumption most likely to vary. | A narrow price advantage may disappear when quantities or service frequency change. |
Illustrative example: option A costs $12,000 plus $1,800 annually for five years; B costs $15,000 plus $900 annually. Undiscounted totals are $21,000 and $19,500, excluding any other costs. Different timing or replacement assumptions can change the comparison.
Life-cycle cost analysis compares alternatives over a period of operation. US Department of Energy — Life-cycle cost Source consulted on .